Village of Brownville, NY Anticipated Water Line Construction Schedule
2025 **This timeline is a tentative schedule and subject to change. September Bridge Street Maple Street Rice Street October Patrician Lane St. Lawrence Avenue November St. Lawrence Avenue continued December Watertower Drive Pike Street Remaining village streets will resume in the spring of 2026. Schedule details willow follow. Village of Brownville Water Project Update
Residents can expect to see equipment, piping, and other construction materials throughout the village beginning in late July 2025. Construction is scheduled to officially begin on August 4, 2025, starting on St. Lawrence Avenue West, Franklin Street, and Watertower Drive. Crews will then move on to Potter Street and Warren Street. Work will continue throughout the Village through December 22, 2025, pause for the winter, and resume in late March 2026. The project is expected to be completed by the end of 2026. Please be patient and expect traffic delays as crews work throughout the Village. We will do our best to notify residents in advance of any water service disruptions or construction happening directly in front of driveways. To receive immediate project updates and important Village alerts, text BROWNVILLE to 24639 to sign up for text, email, or phone notifications. For assistance, please contact the Village Office. |
|